Friday, 14 August 2015

Site visit 13.08.15

Cunliffe brick remedials to complete

Bean Hall- vales to review acoustic panel re AV screen size/ location

Bean Hall- ply panels damaged- replace

Ditto

Ditto- water supply not required to face of servery- replace panel

Ditto rub out marks or replace

Ditto

Damage to ply panels to servery- replace

BE.EX.ED.00.01- remove ALL ironmongery before decorating and replace ALL ironmongery/ rehang door
Old Bean GFL under link- make good brickwork adjacent paving- out of sequence

Cunliffe under link- complete brickshield before landscape- out of sequence

HCL to advise matwell frame BE.ED.00.06- steps out from wall- infill material or adjust? Advise

Ditto adjacent stair- HCL to advise

Lockers/ opening formed mismatched- packing or infill required- HCL to advise

1st floor Bean corridor leading to reading room- in progress

BE.ID.01.03- brick treatment/ cut required but oak frame already installed- out of sequence works- HCL to advise/ protect to complete

Bean stair refurb- HCL to advise on brick doctor/ aluminium pressing to corners

Seminar stair- work required to slurry wall/ perimeter to 1st floor fire rated windows- Action HCL

Seminar stair rooflight opening nearing completion- awaiting sailblind

Attenuating cowls sitting too high above roof finish- radius to fitting does not accommodate build up of lead over duct- HCL to remake lower section of cowls and refit
 Ditto- otherwise visible in elevation. No sample or drawing issued or approved by design team. HCL to address problem.

TEK vent fitted but drawings not finalised and comments not accommodated. Unit projects beyond face of brick as CVA comments- must be set back and continual weathering added over. Also not metal profile fitted to brickshield. Complete and refit as comments- Action HCL

Ditto brickshield reveal- not as CVA specification- Rebuild as required- Action HCL- raised previously

Ditto TEK vent- internal finishes to be addressed also- Action HCL

Acoustic panels not fitted and CVA setting out issued- Rehang- Action HCL

1st bay to arcade- 2 No. bolts projecting/ brick to be made good/ staple removed- Action HCL

Ditto- remove staining to brickwork- Action HCL

Bean Hall- induction loop being fitted- HCL to ensure protected until carpet fitted- Action HCL

Bean refurb steelwork- decorations in progress

Bean 1FL- emergency exit sign should be centralised over brick opening as CVA setting out- Action HCL

Downpipe to be added externally 1 FL triangle roof- Action HCL

Oak to match adjacent to vaulting 1FL Bean refurb- Action HCL

Cunliffe stair- panelling underway

CU.ID.00.15- carpet/ tiling interface not level- HCL to address

Oak linings underway to Bean 1FL- Action HCL