Site visit 03.04.14

 Damage to precast beam from CCP- to be made good

 Site overview

 Naylor Lintols on site for Cunliffe openings

 CCP Precast beams for hall G/L 2

 Discrepancy to concrete wall G/L C
 Defective head to CCP columns to G/L 2- CCP to make good

 Ditto

 Ditto

 Cunliffe- 1st floor slab poured

 Ditto
 Reinforcement for 1Fl columns

 Reinforcement for 1FL landing

 Reinforcement for insitu half landing

Flexcell Interface between new build and existing Cunliffe slab

 Overview of Bean LRC

 Overview of Cunliffe stair

 Awaiting formwork/ concrete where gable removed to Cunliffe

 Existing Bean- excavation for footing to new inserted steelwork

 excavation for goalpost to old Bean G/L 4

 Setting out of landing to bean stair- HCL to check level

 Underside of Cunliffe 1FL slab precast panels is clean following pour

 Ditto

 HRW to check set out of kickers/ walls supporting seminar stair precast elements

Opening formed to old Bean- temporary support

 Columns G/L 2- defective finish to head to be made good

Cunliffe stair- awaiting pour of landing.