HRW Site Visit - 28.03.14.
Reason for visit: inspection of Cunliffe 1st floor slab and further progress to Bean RC.
Wall with blown reinforcement (to left, under formwork)
Honeycombing to column
Ditto
Propping to rear wall of existing Bean
Pier to be supported by plate on new frame
Work underway for underpining to Bean
Cunliffe 1st floor reinforcement
Bow to end of shear wall with blown formwork
Ditto (other end)
Worst deformation due to blown reinforcement
Ditto, from other end showing steps in surface of wall