Site Visit 06.03.14

 concrete pour underway for first phase of columns

Lift shaft pour complete. Honeycombing to base wall corner  G/L A - Hutton to provide details of proposed site remediation

GFL columns formwork struck

 cill to lift shaft formed as per requirements for Schindler lift

 Additional pour required

 Reinforcement underway for walls G/L A

Damage to existing Bean brickwork during demolition- to be made good

Formwork to Cunliffe columns- poured- awaiting to be struck G/L 7

Awaiting reinforcement- Cunliffe  G/L F/7

Formwork struck to remaining columns Cunliffe G/L 7

Reinforcement underway to corner of Cunliffe G/L G/7

Repairs to Bean Arch- Order to be placed for handmade bricks

Honeycombing to base of column G/L D/7- Hutton to provide details of proposed site remediation

Reinforcement now stored on slab as HRW comments

Lift shaft/ G/L A

Temporary support installed and opening formed to GFL Bean existing wall adjacent G/L 4

Ditto

Honeycombing to base of column G/L E/4- Hutton to provide details of proposed site remediation