Monday, 24 March 2014

Site Visit 20+21.03.14

 Site overview- concrete frame GFL underway to Bean

 First arch cast to GFL

 Honeycombing/ pitting G/L D

 Ditto

 Pitting high level to column G/L C/2

 Pitting at low level

 Ditto- remedial works required

 Poor edge formed to Cunliffe stair wall G/L F/7

 Also pitting at high level to same location

 Ditto

 Soil pipe cracked G/L C/7

 Temporary propping to Old Bean GFL

 Additional lintols required to support brickwork where new openings formed G/L E-F/1

 Crane on site lifting Demi-dec into position for 1FL Cunliffe slab

 Ditto

 Ditto

 View of Cunliffe demi-dec from underside

 Ditto

 Demi-dec finish good

 Additional works required to take back brick to LHS. Tolerance currently all taken up to G/L 4

 Top of demi-dec- installation underway

 Column/ demi-dec interface
 
 HCL remedial works carried out- prior to forwarding method statement for comments

Demi-dec installation underway