Tuesday, 15 April 2014

Site Visit 09.04.14

Temporary propping in preparation for double T precast concrete slabs to Bean LRC Hall

 Precast column made good- awaiting beam/ grout. Top surface still unlevel

 Further making good to column

 Pitting and making good to column G/L B/2- still poor

  Pitting and making good to column gridline C/ 2

 G/L C-D/ 2- making good to precast column poor

 Temporary support underway

 Ditto

 Reinforcement for concrete support wall to seminar stair

 CVA to forward information of remedial works required to concrete wall  G/L C

 Footing cast for picture frame to Bean LRC refurb

Pad cast for steelwork to Bean LRC refurb G/L B-C

 Cunliffe- ground floor half landing cast- East stair

 Cunliffe First floor landing cast- East stair

 Cunliffe 1st floor- falsework under construction for insitu columns

 Overview- Cunliffe to Bean LRC

Cunliffe 1st floor

 Cunliffe East Stair

Scaffold erected around Bean LRC refurb section