Tuesday, 15 September 2015

site visit 10 + 11.09.15

 Bean seminar stair- making good/ decorations underway. Awaiting trim to perimeter of fire rated windows
 Pointing still to be carried out to arches- not continuous as previously raised

 Pointing to parapet ongoing to Bean arcade

 Mastis required to arches and completion of all fineline trims

 Ditto

 Movement joint- mastic to parapet to be completed

 Cunliffe tile sorting still unacceptable as previous comments

 Awaiting carpet and metal paneling to Bean Hall

 Joinery installed to Bean GFL cloakroom

 HCL to address poor interface with drylining in this location

 Replacement door fitted to Bean LRC refurb Marshalls office

 Concrete to kerb incorrect- HCL to address

Ditto

 Capping to be mitred to corners as per Ibstock details

Ditto 

 Stage lawn to be repaired as damaged during construction as not adequately protected. Lime mortar repairs only. All at HCL's cost

 Ditto

 All manhles to be refitted with inset type as specified. Current covers temporary only. HCL to advise when switch will occur and provide comprehensive schedule as requested

 Cunliffe south elevation. Glazed brick repaired but pointing to trespa to be removed

 Final Cunliffe remedials underway

 Bean/ Cunliffe brickwork interface still unacceptable as raised previously- HCL to address

 Cunliffe hit and miss- mastic poor quality workmanship- replace

Ditto

Gas pipe to be painted in Umbra grey

 Reference panels to now be removed