Bean LRC picture frame awaiting cut back of existing slab prior to concrete pour
Seminar stair falsework
Ditto
Hall precast exposed
Precast beam/ Double T interface
Ditto
2nd picture frame- awaiting pour
Ditto
Holes made to web of steel on site- against CVA comments. All to be made good at HCL costs. Method statement to be forwarded by R+M for CVA comments
Additional Old Bean Steel installed
Cunliffe 2 FL slab pour underway
Ditto
Existing gables to old Cunliffe retained
Pour underway
Crack to Cunliffe column- making good required. HCL to advise how make up between old and new Cunliffe slab will be carried out
New Bean LRC 1Fl falsework underway
Ditto
Cunliffe Stair/ landings underway
Bean connections between insitu walls and slab
Old Bean LRC- concrete cover to picture frame steels
Discrepancy between existing and new Cunliffe slabs- HCL to survey and advise of extent of variation- 1FL
Works required to 1FL Cunliffe steel
HRW requesting intermediate lintel to be retained- HRW to confirm following site visit
Cunliffe 2FL slab completed
Ditto
Netting required to Cunliffe scaffold- debris reported outside site boundary. Action HCL
Bean LRC connections for insitu concrete 1FL
Rebar installation 1FL Bean LRC
Gutter works may be required- retained old Bean
Footings for reference panels- to be constructed w/c 5/1
Netting required to Cunliffe scaffold- debris reported outside site boundary. Action HCL