Monday, 19 May 2014

Site Visit 16.05.14

 Cunliffe Gable reference panel completed- CVA comments to follow

 Cunliffe south elevation facework panel complete- CVA comments to follow

  Cunliffe hit and miss panel complete- CVA comments to follow

 Falsework to G/L 1 where HCL modifications due to cover requirements on projecting reinforcement within cavity. HCL still to forward details of insulation to adapted detail- Action HCL

 Bean LRC 1FL slab cast.

 Bean Hall GFL

 Seminar Stair- stepped wall cast awaiting precast elements

 Reinforcement to 1FL dwarf wall Bean LRC

 Reinforcement to 1FL Bean- caps required- Action HCL

 Awaiting bridge falsework between Bean & Cunliffe

 Reinforcement to Seminar stair stepped wall- awaiting pour

 Refurbished Bean LRC GFL- CVA to confirm removal of tiles/ lining detail if not provided- CVA to check contract documents

 1FL Cunliffe - blockwork underway

 Cunliffe- falsework for new stair landings underway

 Bean LRC- 1FL slab overview

 Cunliffe G/L 1- ring bean demolition incorrect. Detail not as survey- CVA/ HRW to review

 HCL check to coverage of rebar to 2FL slab- HCL to report back on investigation

 Bean LRC GFL- brickwork over steel condemned- still in situ. HCL to confirm date for rebuild

 Scaffold board missing- HCL to address immediately