Infill material to Bean LRC 1FL slab to be discussed following Cornish change to Double T strategy. Service void preferences to be reviewed
Brick corbel detail below pier to be reviewed to Seminar stair- does not comply with BS on brickwork. CVA to advise on changes required
Bridge slab falsework/ reinforcement underway
Reinforcement bars left unprotected- Action HCL
Minimum coverage to be maintained to kickers/ walls- Action HCL
Ditto
Awaiting method Statement from R&M regarding making good to drilled steels
AV cupboard required behind wheelchair space to foot of stairs. AV minutes/ info to follow
Further making good to Cornish concrete will be required- beam interface
Glass samples- Alucraft. CVA to confirm acceptance following review of all drawings
Scaffold- gap to be closed- Urgent action HCL