Detail of reinforcement Gridline 1/B- U bars on double-T panels project beyond proposed insitu beam line by 10mm and require 25mm coverage. HCL to advise of remedial works to concrete to ensure correct coverage and alternative higher performing insulation to ensure cavity is fully maintained and required U value also achieved. Action HCL
Ditto
Reinforcement underway to Bean LRC slab
Ditto
Opening for stair Bean LRC
Brickwork over steel to Old Bean completed but incorrectly set out- condemned. HCL to rebuild- see below:
Brickwork to LHS of beam set back
Brickwork to RHS of beam projecting. Line is also inconsistent. Condemned.
View of opening with temporary support removed- into seminar stair space.
Reinforcement placement adjusted to correct setting out to seminar stair
Ditto
Concrete slab to 2FL Cunliffe- depressions shows trace of reinforcement beneath- see below:
Surface cracking evident to new Cunliffe 2FL slab
Ditto. HCL to investigate and ensure adequate coverage provided to slab throughout.
Cunliffe stair removed in lieu of new precast stair
Overview of Bean LRC 1FL slab- remaining reinforcement underway