Friday, 27 June 2014

Site visit 26.06.14

 Lighting mock up to Bean

 Level to be adjusted following review of lighting levels/ positions

 Overview of Bean- falsework struck

 falsework adjacent precast GFL beam G/L 1- to be removed carefully

 HCL to schedule all areas where concrete remedials required

 RIW applied to concrete

 HCL/ HRW to advise on cracking to arch BE.EW.00.06

 HCL to schedule all areas where concrete remedials required- here G/L D/ 2-3 GFL

 Ditto
 Brick infill above still to Bean refurb GFL relaid

 Seminar stair/ arches

 1FL general reading space- falsework struck

 Concrete remedials required to all 1FL arches-  HCL to schedule all areas where concrete remedials required

 Ditto
 Ditto BE.EW.01.10
 Ditto BE.EW.01.01
 Scabbling underway to Bean arch BE.EW.01.03

 1FL Reading room overview

 Arch reference panel- CVA mark up comments to follow

 Fillet to arch not flush with face

 Ditto

 Internal face of panel

 Cunliffe relief panel- glazed bricks added. Issues regarding porosity of brick and number of courses laid at one interval.
 Cunliffe gable panel complete. Capping mortar joints not uniform. DPC detail to be checked