Level to be adjusted following review of lighting levels/ positions
Overview of Bean- falsework struck
falsework adjacent precast GFL beam G/L 1- to be removed carefully
HCL to schedule all areas where concrete remedials required
RIW applied to concrete
HCL/ HRW to advise on cracking to arch BE.EW.00.06
HCL to schedule all areas where concrete remedials required- here G/L D/ 2-3 GFL
Ditto
Brick infill above still to Bean refurb GFL relaid
Seminar stair/ arches
1FL general reading space- falsework struck
Concrete remedials required to all 1FL arches- HCL to schedule all areas where concrete remedials required
Ditto
Ditto BE.EW.01.10
Ditto BE.EW.01.01
Scabbling underway to Bean arch BE.EW.01.03
1FL Reading room overview
Arch reference panel- CVA mark up comments to follow
Fillet to arch not flush with face
Ditto
Internal face of panel
Cunliffe relief panel- glazed bricks added. Issues regarding porosity of brick and number of courses laid at one interval.
Cunliffe gable panel complete. Capping mortar joints not uniform. DPC detail to be checked