Site visit 12.06.14

Underside of seminar stair prior to grouting of steps

Care to be taken around precast when removing falsework to Gridline 1 beam

Bean stair postion/ landing to be repositioned- landing location to be adjusted

Ditto

Seminar stair- precast installed

Precast stair detail
Seminar stair grouting underway

Arch formwork to 1FL reading room underway

Ditto

Rebar to G/L A
Cunliffe stair precast installation complete East Stair

Ditto

Arch reference panel reconstruction underway- fillet to start 3 courses above spring point. larger to be used to infill below

Inner face good
Out of plumb from formwork- tolerances to be checked against spec.

Cunliffe gable panel rebuilt- awaiting cappings

Rear of panel. HCL requested mortar fillet to projections within cavity. CVA to confirm with Ibstock/ building control