Underside of seminar stair prior to grouting of steps
Care to be taken around precast when removing falsework to Gridline 1 beam
Bean stair postion/ landing to be repositioned- landing location to be adjusted
Ditto
Seminar stair- precast installed
Precast stair detail
Seminar stair grouting underway
Arch formwork to 1FL reading room underway
Ditto
Rebar to G/L A
Cunliffe stair precast installation complete East Stair
Ditto
Arch reference panel reconstruction underway- fillet to start 3 courses above spring point. larger to be used to infill below
Inner face good
Out of plumb from formwork- tolerances to be checked against spec.
Cunliffe gable panel rebuilt- awaiting cappings
Rear of panel. HCL requested mortar fillet to projections within cavity. CVA to confirm with Ibstock/ building control