 Cunliffe demolition completed. Bricking in of openings/ forming of new openings to commence shortly.
 Bean LRC foundations laid


 Ditto

 Removal of remaining tarmac to former car park underway

 Bean footings

 Marking up of Cunliffe foundations underway

 Ditto

 Opening up works to Cunliffe GFL slab

 Redundant services removed- Cunliffe GFL

 Bean LRC- paint peeling to ceiling

 Bean GFL- Beam exposed

Bean LRC- existing building- corridor stripped

  Bean foundations

Ditto